DOOWIN mono buoyancy bags performed well in the world’s first ultra-large and ultra-long HDPE double-tube shipping and installation.

Recently, a super flexible HDPE submarine pipeline came into use at the commercial port of the Saudi Arabian Sea City. The submarine pipeline is 558.2 meters long and 1,315 tons weight. Finally, it successfully adopted double-tube shipping to achieve seamless underwater docking. So, it became the world’s first super flexible HDPE submarine pipeline. Double pipe shipment installation.

This project was operated by The Second Engineering Company of CCCC Fourth Harbor Engineering Co.,Ltd

Data flow: Where is the difficulty in installing dual-tube shipments?

The installation of HDPE submarine pipelines is the first in the world.

The climatic conditions of the construction site are complex. Meanwhile, the wave height of more than 0.5 meters has an impact on the pipeline transportation. So,  the installation accuracy requirements are very strict.

To sum up, a single strip of HDPE pipe requires 190 welds. so all the pipes will require total of 4,976 welds. Moreover, the weld must completely seamlessly connect with each other.

The underwater installation is the deepest into the water 11 meters.

Let’s explore the three difficulties of dual-tube shipping installation!

Difficulties 1: Hard to ship on land

Pipeline buoyancy

HDPE single pipe is 558 meters long, and the total length of double pipe is 1116 meters. It is the world’s first in single shipment. The single pipe has a diameter of 1.8 meters,  and it is currently the second largest in the world. The double pipe is welded by 186 standard pipes, and weighs 1,315 tons.

In conclusion, such a huge pipe from land to sea requires multiple equipment to work together. Onshore winch, offshore tug, tube tail loader.

So, such a behemoth must be interlocked, with the same force, uniform speed, and slight accidental damage.

Difficult 2: Difficult to haul at sea

pipeline installation

The double pipe shipment needs adjusting by positioning, car recycling, sea hauling, entering narrow basement and so on. The pipeline needs to travel 9 kilometers long distances at sea and stay up to 8 hours on the sea. Dust storms, gusts, big waves and other bad weather around the Red Sea are high, making the risk of pipeline hauling heavy.

Difficulties 3: Pipe docking is difficult

The total length of the pipeline is more than 14 kilometers. So, it divides into 17 installations and requires 15 double pipe docking under the sea. Moreover, the docking requirements are seamless and balancing. After the docking finish, the pipeline is filled with water and the axis is precisely aligned. In additong, without wind and waves, it is still necessary to work continuously day and night, so the work intensity is very large.

pipeline buoyancy project

Technological innovation

Creativity will move the docking at sea to the shore, and make a “pre-docking” adjustment on the land. It ensures the two interfaces can connect together  seamlessly. At the same time, in the docking phase at sea, the team adopt the combination of divers and high-precision GPS in order to monitor and adjust the whole process. It ensures accurate positioning of pipelines and meet the requirements of design specifications.

Pipeline installation use mono buoyancy bag

The flexible HDPE submarine pipeline project has been listed as one of the three technical difficulties in the construction of the Saudi Jizan Economic City. The CCCC Four Harbor Engineering have overcome this world-class problem through independent technology research and development, with good performance of DOOWIN mono buoyancy bags. The designers of the Economic City have found it difficult for the Europeans and Americans. The Saudis have greatly praised the construction of the CCCC Four Harbor Engineering company.

best-buoyancy-units